  • Important Milestones in the Development of the Port
    MilestoneDate
      Declaration of 12.80m draught facility for berthing of Panamax class vessels   19-11-2011
      Merger of Cargo Handling Labour Division with V.O. Chidambaranar Port Trust   27-07-2011
      Launching of Passenger Ferry Service, Tuticorin -Colombo   13-06-2011
      Inauguration of Passenger Terminal   06-03-2011
      Name Change as V.O. Chidambaranar Port Trust   11-02-2011
      Inauguration of construction of North Cargo Berth-II   24-01-2011
      Inauguration of Capital Dredging   30-12-2010
      Inauguration of Replaced Wharf Crane in VOC Berth   01-07-2010
      Signing of Sister Port Agreement with Gijon Port, Spain   21-04-2010
      Commissioning of Berth No.9   14-07-2008
      ISO 14001 : 2004 Certificate of Approval   16-09-2005
      Silver Jubilee Celebration   10-07-2004
      Inclusion of our port in Western Circuit of Cruise Tourism   26-12-2003
      Completion of Dredging Dock Basin in front of berth No.8   24-09-2003
      Introduction of direct main line service to Europe   16-07-2003
      Entering 30th year of existence as a Major Port   11-07-2003
      Switchover to ISO 9001:2000 standards   23-04-2003
      Commissioning of Berth No.8   02-02-2002
      Introduction of main line service to U.S.   17-10-2001
      Functioning of a world standard Container Terminal   21-12-1999
      Completion of Dredging in Harbour Basin (11.90m) and Approach Channel (12.50m)   05-11-1999
      Commissioning of shallow draught berth   10-05-1999
      Licensing out berth no 7 to M/S PSA-SICAL   15-07-1998
      Commissioning of alongside berth 7   05-09-1998
      Introduction of Night navigation   12-10-1996
      Certification of ISO 9002   12-03-1996
      Commissioning of Coal jetty II   27-02-1995
      Commissioning of sixth alongside berth (AB 2)   01-01-1984
      Commissioning of fifth alongside berth (AB 1)   09-05-1983
      Commissioning Coal jetty I   01-03-1983
      Commissioning of Oil Jetty   26-04-1980
      Constitution of the Port Trust Board   01-04-1979
      Commissioning of the next two alongside berths (VOC III & IV)   31-12-1975
      Commissioning of the first two alongside berths (VOC I & II)   02-12-1975
      Commissioning of the Oil mooring berth   13-07-1974
      Declaration of Tuticorin Port as a major Port   11-07-1974